Cloud Provider Network Maintenance
Scheduled Maintenance Report for Bloomreach
Completed
The scheduled maintenance has been completed.
Posted Mar 13, 2020 - 13:01 CET
Update
Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Mar 13, 2020 - 04:46 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 13, 2020 - 04:01 CET
Scheduled
Start:
Thu Mar 12 20:00 2020 (PDT)
Fri Mar 13 03:00 2020 (UTC)
End:
Fri Mar 13 03:00 2020 (PDT)
Fri Mar 13 12:00 2020 (UTC)


Details:

On Thursday, March 12, 2020 from 8:00 PM PT until March 13, 2020 at 5:00 AM PT, our upstream ISP will be performing scheduled maintenance to multiple circuits. This maintenance is a continuance of previous maintenance to relocate fiber cabling. Engineering teams will be on standby throughout the maintenance window.

DURATION: The maintenance is scheduled to take 9 hours.

IMPACT: Our network infrastructure makes use of dual-path design. Workloads will be transferred to redundant circuits where possible. Due to the nature of this effort, we expect there will be brief, intermittent periods during the maintenance window where traffic is disrupted or latency is degraded.
Posted Mar 12, 2020 - 08:55 CET
This scheduled maintenance affected: Bloomreach Cloud (Bloomreach Cloud US).