Start: Thu Mar 13 20:00 2020 (PDT) Fri Mar 14 03:00 2020 (UTC) End: Fri Mar 14 05:00 2020 (PDT) Fri Mar 14 12:00 2020 (UTC)
Details:
On Friday, March 13, 2020 from 8:00 PM PT until March 14, 2020 at 5:00 AM PT, our upstream ISP will be performing scheduled maintenance to multiple circuits. This maintenance is a continuance of previous maintenance to relocate fiber cabling for capacity upgrades. Engineering teams will be on standby throughout the maintenance window.
DURATION: The maintenance is scheduled to take 9 hours.
IMPACT: Our network infrastructure makes use of dual-path design. Workloads will be transferred to redundant circuits where possible. Due to the nature of this effort, we expect there will be brief, intermittent periods during the maintenance window where traffic is disrupted or latency is degraded.