Cloud Provider Network Mainteance (Part III)
Scheduled Maintenance Report for Bloomreach
Completed
The scheduled maintenance has been completed.
Posted Mar 15, 2020 - 13:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 15, 2020 - 04:00 CET
Scheduled
Start:
Sat Mar 14 20:00 2020 (PDT)
Sun Mar 15 03:00 2020 (UTC)

End:
Sun Mar 15 05:00 2020 (PDT)
Sun Mar 15 12:00 2020 (UTC)


Details:

On Saturday, March 14, 2020 from 8:00 PM PT until March 15, 2020 at 5:00 AM PT, our upstream ISP will be performing scheduled maintenance to multiple circuits. This maintenance is a continuance of previous maintenance to relocate fiber cabling for capacity upgrades. Engineering teams will be on standby throughout the maintenance window.

DURATION: The maintenance is scheduled to take 9 hours.

IMPACT: Our network infrastructure makes use of dual-path design. Workloads will be transferred to redundant circuits where possible. Due to the nature of this effort, we expect there will be brief, intermittent periods during the maintenance window where traffic is disrupted or latency is degraded.
Posted Mar 15, 2020 - 04:00 CET
This scheduled maintenance affected: Bloomreach Cloud (Bloomreach Cloud US).